Cell degradation / LFP graphite
Advanced life time modeling
Explore a Monte Carlo simulation of a 280 Ah prismatic LFP/graphite cell: 400 simulated lifetimes per utilization profile.
The operating history anchors three future duty scenarios through service year 25.
400 simulated lifetimes per scenario
Monte Carlo lifetime simulation
Monte Carlo simulation samples uncertain cell parameters and future utilization to produce a range of possible capacity outcomes.
Selected year
Monte Carlo degradation histogram
- Baseline duty
- Higher stress
Lifetime capacity retention chart
- Modeled operating history
- Baseline duty
- Higher stress
Move the slider to update both charts.
Loading the model example…
Cell configuration & utilization
- Cell: 280 Ah prismatic LFP/graphite, rated at 896 Wh.
- Duration: 3.5 hours; higher stress uses full rated power. Hotter / lower usage combines elevated temperature with lighter cycling.
- Monte Carlo: 400 simulated lifetimes per profile, projected through year 25.
| Assumption | Baseline duty | Higher stress | Hotter / lower usage |
|---|---|---|---|
| Cycling | 240 EFC/year | 340 EFC/year | 120 EFC/year |
| Cycle depth | 75% | 100% | 50% |
| Mean SOC | 52% | 70% | 52% |
| Charge rate | 0.20 C | 0.286 C | 0.20 C |
| Mean temperature | 25 °C | 32 °C | 35 °C |
| Seasonal swing | ±7 °C | ±8 °C | ±7 °C |
| Future duty variation | 8% | 12% | 8% |
Explore a site-specific model.
aAugment can discuss site modeling, partnerships, and investment opportunities.
Contact aAugmentFleet scale / Capacity opportunity
US grid energy storage market.
Explore how battery aging creates a growing need to restore capacity across the U.S. grid.
Site availability is suffering.Interconnections are underutilized.
- State-of-charge imbalance
- Uneven charge levels create curtailed system limits.
- Service outages
- Sites experience longer or more frequent outages for module or HVAC maintenance.
- Battery degradation
- The market model assumes approximately 2% annual degradation.
U.S. grid / Modeled degraded capacity
- $3bnDegraded capacity / 2027
- $13bnDegraded capacity / 2037
- ~16%Annual growth / 2027–2037

These estimates value degraded capacity. They do not represent service revenue or a pipeline of qualified projects.
This fleet outlook is separate from the synthetic cell example above.
View site infrastructure constraints ↗Capacity and site performance
What reaches the interconnection?
Annual average available capacity at the interconnection, by year after commissioning. Offline capacity is fixed at 8%.
- Selected site / AC MWh at POI
- Year 5 after commissioning
- —
- Original plan / AC MWh at POI
- Year 5 after commissioning
- —
- Augmentation delta / AC MWh at POI
- Year 5 after commissioning
- —
Assumptions and what this demo leaves out
- Original site: 400 MWh LV reference energy. Added units are installed at year 0 and age alongside the original fleet.
- Both cohorts lose 2.5% capacity annually. SOC imbalance makes 8% of their remaining reference energy inaccessible.
- Annual average offline capacity is fixed at 8% of remaining energy for both cohorts, separate from SOC imbalance.
- Conversion consumes 6% of accessible energy. Aging, imbalance, offline, and conversion losses scale with the combined fleet.
- Original plan means no augmentation at the selected age. The floating delta spans original-plan capacity to selected-site capacity.
- This is a full-charge energy screen, not instantaneous SOC. Power, thermal limits, and actual site performance are not evaluated.
Daily operation / Energy capacity
Daily dispatch with augmentation.
Each use case compares baseline dispatch with the selected energy capacity at a fixed 100 MW power rating.
- 100 MW battery power
- 100 MW interconnection
- 200 MWh / 2 h base system
Loading dispatch example…
Green: selected battery. Gray: no augmentation. Gray edges around green indicate identical dispatch.
Positive power exports; negative power charges.
- Site operating margin / day
- —
- Incremental after capacity cost / day
- —
Only MWh changes. Battery power and the interconnection remain fixed at 100 MW.
Assumptions and what this demo leaves out
- Every curve uses invented prices and a fictional site. ERCOT-style describes the example, not historical ERCOT data.
- Each day is optimized with perfect price foresight, 15-minute intervals, and no simultaneous battery charging and discharging.
- Usable capacity is AC-discharge-equivalent MWh. The base battery can deliver 100 MW for two hours from full.
- Round-trip efficiency is 90%. Storage starts and ends empty; no initial energy is supplied for free.
- Battery charging and discharging each have a 100 MW limit. Combined site export never exceeds 100 MW.
- Solar is capped at 150 MW generation. Solar-only charging and curtailment are allowed; grid charging is disabled.
- Other scenarios allow up to 100 MW grid import. Peak support earns the displayed fictional delivery credit.
- Operating margin equals export receipts minus grid purchases and battery variable cost, plus any peak-delivery credit.
- Battery variable cost is $3 per MWh discharged. Negative-price grid purchases appear as a credit, not a positive cost.
- Added capacity costs $140/kWh installed and $4/kWh-year maintenance. Capital recovery assumes 8% over 15 years.
- Daily capacity cost allocates annualized capital and maintenance over 365 days; it does not annualize this day’s earnings.
- Existing fixed costs cancel in incremental comparisons. Taxes, replacement, terminal costs, market qualification, and actual investment returns are excluded.
Lifetime site plan / Investment returns
What does the lifetime site plan return?
The 100 MWh site adds four battery cohorts across 15 years. Compare financial cases and sensitivities.
Base case selected
Fixed additions: years 4, 7, 10, and 14. Adjust financial assumptions below.
- Incremental NPV / incl. residual
- —
- Added capital / PV vs. original cost
- —
- Added profit + residual / PV uplift
- —
- Augmentation IRR / incl. residual
- —
Capacity and site performance
How much room is there for disappointment?
Stress the same investment with invented cost, revenue, and degradation variation. Compare outcomes when commissioning slips.
600 synthetic draws / Four-addition site plan
Change the economics above to shift this distribution. The end date stays fixed when commissioning is delayed.
- P10 NPV
- —
- Median NPV
- —
- P90 NPV
- —
- Draws with positive NPV
- —
Assumptions and what this demo leaves out
- Independent triangular cost and revenue multipliers span the selected ± range, centered on the selected finance inputs.
- Added-cohort annual decline is sampled between 0.5% and 2%, with a 1% mode.
- Delay shifts all four additions. Campaigns after year 15 are excluded; no purchase commitments are assumed.
- Draw shares and percentiles describe invented scenarios. They are not calibrated probabilities or investment recommendations.
- The site plan’s residual-value convention is retained. Correlated risks, outages, market qualification, and real price forecasts are not sampled.